07 January 2013

P L U M B I N G . E L E C T R I C A L


holidays and rain delays coupled with an added 4 week window lead time has focused our (very slow) forward
progress on the interiors. because the client wanted to purchase all fixtures, outlets, lighting, and appliances
independently, it has made drawing coordination for heights and sizes more difficult and resulted in a lot of
drawing holes directly onto walls. but all of the plumbing and electrical is prepped for outlets and fixtures and the
tortoise-esque speed has allowed us to point out potentially awkward conditions and interactions (like the
housing sizes and placement for integral lighting or the heights of the wall mounted toilets below) that we are
crossing our fingers will get resolved cleanly.